Berlin Brandenburg Airport (BER): One Main Terminal Between Two Runways, Nine Years After the Date on the Sign
The airport was supposed to open in October 2011. It opened on 31 October 2020, after the fire system failed its acceptance test, the projected bill passed six billion euros, and a terminal built for 28 million passengers sat finished and empty. The last airlines completed their move from Tegel by 8 November 2020. Berlin has had one commercial airport ever since.
Nine Years Late, and the Record Is Unusually Complete
The airport was planned for October 2011, five years after construction started in 2006. It opened on 31 October 2020. The distance between those two Octobers is nine years, and the reasons are documented in a way that most delays are not.
The decision to build one airport for the reunited capital was taken early. After the Wall fell in 1989 and reunification followed in 1990, Berlin became the federal capital again, and its three airports, Tegel, Schönefeld and Tempelhof, were old and increasingly crowded. The states and the federal government settled on the single airport concept: one new airport would serve Berlin and Brandenburg, and the others would close.
The holding company was founded on 2 May 1991, owned 37 percent by Berlin, 37 percent by Brandenburg and 26 percent by the federal republic. Site selection took years. Sperenberg, Jüterbog East, Jüterbog West, Tietzow, Michelsdorf, Borkheide and Schönefeld South were all assessed. On 28 May 1996 the Mayor of Berlin, the Minister President of Brandenburg and the federal transport minister committed to Schönefeld. The decision was called the consensus decision, and it survived the court cases that followed.
Privatisation collapsed first. A consortium led by Hochtief won the bid in September 1998, a rival consortium sued, and the Brandenburg court annulled the award in August 1999. The two groups then bid together, and in May 2003 the board scrapped the privatisation altogether. The airport would be public, owned by Berlin, Brandenburg and the federal government.
The construction permit came from the Brandenburg infrastructure ministry on 13 August 2004. Residents sued, and the Federal Administrative Court rejected their arguments on 16 March 2006, with conditions attached. The most consequential condition was that fewer people would live under the approach path than lived around the three existing airports. That made the closure of Tegel and Schönefeld a legal requirement rather than a policy choice.
Construction began in 2006 with an opening planned for October 2011. As that date approached, the marketing used 2 June 2012. Neither date held. The airport received its operating licence in May 2020 and opened for commercial traffic on 31 October 2020, fourteen years after construction started and twenty nine years after official planning began.
The nine years figure is arithmetic. October 2011 to October 2020 is nine years. The article also gives fourteen years from the start of construction and twenty nine years from the start of official planning, which are different beginnings for the same project.
The name and the code
The airport is named after Willy Brandt, the Nobel Peace laureate who was mayor of West Berlin from 1957 to 1966 and chancellor of West Germany from 1969 to 1974. The name was decided on 11 December 2009. The IATA code is BER rather than the BBI used during planning, because BBI already belonged to Biju Patnaik Airport in Bhubaneswar, India.
A U Shaped Building, Numbered Like a Floor Plan
Terminal 1 sits between the two runways, directly above the railway station. It is a midfield airport in the literal sense: apron on both sides, trains underneath, and a gate numbering system that runs from A01 to D17 without leaving the building.
The building was designed by gmp, Gerkan, Marg and Partners, the same firm that designed the hexagonal Terminal A at Tegel, which opened in 1974. At Berlin Brandenburg the terminal was placed in the middle of the airfield rather than at its edge. The station is under the floor. The building has four public levels, numbered 0, 1, 2 and 3.
Check in is on level 1, with 118 counters in eight clusters that the airport calls check in aisles, and more than 100 self service machines planned. By May 2015 two extensions had been added on either side of the main hall, each with 12 more counters and eight security lanes, to stop the centre from becoming a bottleneck. The airside area has 35 screening stations, staffed by Securitas Germany.
The apron has 25 jet bridges and another 85 aircraft stands. The boarding and arrival areas are split into three piers: a main pier 715 metres long, and north and south piers at 350 metres each. The main pier has 16 jet bridges, and all but one of them are two level, so that arriving and departing passengers never meet. Level 1 handles Schengen traffic at gates A01 to A20 and B01 to B20. Level 2 handles non Schengen traffic at C01 to C19 and D01 to D17. Eight gates can take a widebody aircraft and one was designed for the Airbus A380.
The two side piers are not the same. The south pier was reserved almost entirely for Air Berlin and its Oneworld partners, and it has nine single storey jet bridges at gates A30 to A38. The north pier is deliberately more basic: no jet bridges, gates B30 to B45, and passengers walk to the aircraft across the apron. That is the part of the building built for low cost carriers.
The mezzanine at gates A21 and A22 and B21 exists for one reason: extra pre boarding security for flights to the United States and Israel. Lufthansa has a lounge at the north end of the main pier at gate B20, and the airport runs its own lounge at the south end at gate A20. On the main pier, the gate letter follows the level.
| Building | Status | Capacity | Role |
|---|---|---|---|
| Terminal 1 | Open since 31 October 2020 | 28 million | The U shaped main building between the runways, sections A, B, C and D, above the station |
| Terminal 2 | Open since 24 March 2022 | 6 million | A basic departures and arrivals hall next to Terminal 1, sharing its northern pier and airside area |
| Terminal 5 | Closed permanently since 2022 | 12 million | The former Schönefeld terminal buildings, used for less than four months of passenger service |
The U shape has a cost. The main pier is 715 metres long, so a passenger boarding at the far end walks the length of the building after security. The compensation is that the walk is indoors and the station is directly below the check in hall.
One Opened in 2022, the Other Never Came Back
The airport opened with one working terminal and a spare. Terminal 2 had been finished in September 2020 but stayed shut because the pandemic removed the passengers it was built for. It opened on 24 March 2022.
Terminal 2 was announced in March 2016 as a separate low cost facility costing 200 million euros. Construction began in 2018 and finished in September 2020, in time for the original opening plan, and section B, gates 30 to 45, had already been built as part of Terminal 1. The new hall is deliberately basic, connected to the northern pier of Terminal 1 so that both buildings share the same airside area.
Eurowings was supposed to run its Berlin base from Terminal 2. The pandemic kept the building closed instead, and for a while every flight used Terminal 1. By November 2021 demand had recovered enough that Terminal 1 had a capacity problem, so the spare building was finally opened on 24 March 2022 with Ryanair as the main tenant. Wizz Air moved in during November 2022. Eurowings stayed in Terminal 1, which had never been the plan.
The terminal that lasted four months
Terminal 5 was the old Schönefeld terminal, refurbished and renamed. Its four sections became K, L, Q and M, and it was incorporated into the new airport on 25 October 2020, six days before the main opening. It sat on the north side of the site and was connected to Terminals 1 and 2 only on the landside, by S-Bahn and by bus between the new station and the old Schönefeld station. Passengers could not walk between the buildings.
It was meant to run until Terminal 3 opened, which at that point was expected by 2030. Instead it closed on 22 February 2021 because there were not enough passengers to justify it. A vaccination centre opened there in January 2021 and stayed open after the flights stopped. In March 2022 the building was converted into a shelter for refugees fleeing Ukraine. In November 2022 the airport confirmed that Terminal 5 would remain closed permanently, and the airlines that had used it moved to Terminal 2.
Terminal 3 is still on the drawing board. The plan to build it next to Terminal 2 by 2029 was delayed by the pandemic, and no opening date has been fixed. The two open terminals account for 34 million of the 46 million theoretical capacity at opening, which is arithmetic on the article's figures.
Two Parallel Strips, 1,900 Metres Apart, Renamed by the Compass
Berlin Brandenburg has two parallel runways with 1,900 metres between their centrelines. The article states that this spacing allows simultaneous instrument approaches.
| Runway | Length | Surface | History |
|---|---|---|---|
| 06L / 24R | 3,600 m (11,811 ft) | Asphalt concrete | The southern runway of the old Schönefeld Airport, in use since the 1960s, renovated and lengthened from 3,000 m |
| 06R / 24L | 4,000 m (13,123 ft) | Concrete | The new southern runway, commissioned on 31 May 2012 |
The older strip is the reason the airport could reuse part of Schönefeld rather than build everything from nothing. It was renovated and lengthened, and it now carries the 06L and 24R designators. The newer strip is the longer of the two at 4,000 metres and was commissioned in May 2012, years before the terminal beside it was allowed to accept a passenger.
On 3 October 2024 both runways were renamed. The shift in the Earth's magnetic field had moved the compass headings enough that 07L/25R became 06L/24R and 07R/25L became 06R/24L. Nothing physical changed. The paint, the signs, the charts and the approach plates did, which is a reminder that runway numbers are magnetic headings rounded to the nearest ten degrees and not permanent names.
The site covers 1,470 hectares, or 3,632 acres. That is large enough to hold the two runways, the terminal, the cargo module, the maintenance hangars, the government terminal, the exhibition centre and the business parks, with room for the two satellite concourses that are already included in the construction permit. The satellites would raise terminal capacity to 45 million and the runways are described as capable of handling 50 million passengers a year.
A third runway is discussed but not planned. The article says a possible third strip could be located in the south of the site, and that no such plans exist. The expansion that is actually permitted is lateral: two satellites on the apron, linked to the main pier by tunnel, with no further planning consent required.
The Fire System That Kept the Building Empty
The delay was not caused by money, politics or weather. It was caused by smoke extraction, and specifically by a system that could not pass the acceptance test required to let the public inside.
The fire protection and alarm system in the terminal was not built according to the construction permit and failed the mandatory acceptance test run by TÜV. Inspectors found flaws in the wiring, the programming and the implementation of the control system for smoke extractors and fire doors, which had been designed by Siemens and Bosch. The system was complex even by airport standards, and it did not work.
The design made the problem harder. For aesthetic reasons the terminal has smoke extraction ducts in its ceiling but no exhaust to the roof. Smoke was meant to be pushed into a shaft running down through the basement, which required the natural rise of hot air to be reversed. The article states that the system has not worked as planned. Meeting the test required major reconstruction, with the system divided into three areas, at a cost reported as a nine digit figure.
The airport proposed an interim solution using up to 700 human fire spotters. The building supervision department of the Dahme-Spreewald district rejected it. Without a working alarm system and without the spotters, the terminal could not be licensed, and without a licence it could not open.
The people and the paperwork
The fire safety system had been designed by Alfredo di Mauro, whose business cards described him as an engineer. He was qualified as an engineering draughtsman. The airport company dismissed him in early May 2014, citing serious defects in his work and saying that trust in the relationship was finally shattered. His plans, the company said, would be disposed of.
The general planner, Planungsgemeinschaft Flughafen Berlin Brandenburg International, went insolvent, and the architects gmp were dismissed. Inspectors found poor workmanship: cable conduits holding too many cables or incompatible combinations, about 60 kilometres of cooling pipes installed without insulation, and exterior vents in the wrong places that let rainwater into the building.
The one sentence version
A building can be complete and still be unusable. Berlin Brandenburg had a terminal, a railway station underneath it and two runways outside, and it could not admit a passenger because the system that clears smoke in a fire had been designed by someone who was not an engineer. The delay was a safety failure before it was a financial one.
From 2.83 Billion to 9.4 Billion Euros
The 2009 budget was 2.83 billion euros. By late 2012 spending had reached 4.3 billion, almost twice the original figure. By 2015 it was 5.4 billion. The final figure depends on what you count, and the article gives several.
The original financing was assembled from a credit raise of 2.4 billion euros, a bank deposit of 430 million from the owners, and 440 million of equity from the airport company. That structure assumed a 2011 or 2012 opening.
On 3 June 2015 Germany applied to the European Union for approval of 2.5 billion more, which would have taken the total to 6.8 billion, and the airport company said it would be bankrupt by August 2016 if the money was refused. The commission permitted 2.2 billion on 3 August 2016. A loan of 2.4 billion was signed on 13 February 2017, guaranteed by the federal government and the two states.
In May 2016 the estimate stood at 6.9 billion. On 13 January 2018 the company asked for another 2.8 billion for extensions running to 2030, which took the total to 9.4 billion, or 10.3 billion if 900 million of overhead costs for 2019 and 2020 were included. The article also records that the airport's net worth was later claimed to be far below the 4.866 billion carried in the accounts, by as much as 3 billion.
These figures do not reconcile, and the article says so in effect. The 2.83 billion is a construction budget from 2009. The 6.8 billion is a 2015 projection including an EU aid request. The 9.4 billion includes expansion work to 2030. They are different measurements taken at different moments.
There were other bills. Deutsche Bahn sued over the unused railway station beneath the terminal in 2012, and the airport had to pay damages. On 5 May 2016 the Federal Administrative Court decided in favour of 25,500 plaintiffs on the question of ventilating homes whose windows were kept closed for noise, and soundproofing nearby homes became about 50 million euros more expensive as a result.
26 Million Passengers, and the Year It Carried 444,893
The airport handled 26,050,880 passengers in 2025 according to the infobox, on 193,042 movements. The annual table on the same page gives 26,050,740 and a rise of 2 percent. The two totals differ by 140 passengers.
The discrepancy is small and worth stating rather than smoothing over. The infobox says 26,050,880 and an increase of 2.3 percent. The annual table says 26,050,740 and an increase of 2 percent. Both appear in the same article, both are sourced, and neither is obviously a typo. For any practical purpose the figure is about 26 million. The movement count, 193,042, is up 0.7 percent, and cargo reached 52,293 tonnes, up 14.4 percent.
About 135 passengers per movement is arithmetic on the two published totals, and it counts every movement, including small aircraft. Cargo works out at about 271 kilograms per movement, which is low: Berlin is a passenger airport with a thin freighter schedule, not a European cargo hub.
| Year | Passengers | Change | Context |
|---|---|---|---|
| 2020 | 444,893 | first year | Two months of operation in a pandemic year |
| 2021 | 9,947,006 | up 2,135.8% | From a nearly empty base |
| 2022 | 19,845,046 | up 99.5% | Terminal 2 opens in March |
| 2023 | 23,071,865 | up 16.3% | Terminal 2 in service all year |
| 2024 | 25,465,872 | up 10.4% | Approaching the pre pandemic level |
| 2025 | 26,050,740 | up 2% | The annual table figure, see note above |
The comparison that matters is 2019, the last full year before the pandemic, when the two operating Berlin airports together handled 35.6 million passengers. In 2020 that collapsed to 9 million across the city. Berlin Brandenburg has not recovered the old total: 26.05 million against 35.6 million is about 27 percent below, which is arithmetic on the two published figures. The airport is the third busiest in Germany and the twenty fourth busiest in Europe, and it is still carrying fewer people than Tegel and Schönefeld did together.
Four Airlines Call It a Base. None of Them Is Lufthansa.
Condor, easyJet, Eurowings and Sundair operate bases at Berlin Brandenburg. Lufthansa does not use it as a hub, and the long haul map is thinner than the passenger numbers suggest.
The airport was designed around a hub that never arrived. Air Berlin planned to move its primary hub from Tegel to Berlin Brandenburg, and the terminal was built with the connecting passenger in mind: two level jet bridges and a south pier reserved for Air Berlin and its Oneworld partners. Air Berlin filed for insolvency on 15 August 2017 and collapsed on 27 August. Lufthansa bought large parts of it, easyJet took over several routes, and the hub plan died before the building opened.
Lufthansa does not use Berlin Brandenburg as a hub. It flies to Frankfurt and Munich, its own hubs, and hands passengers onto the long haul network there. That is the structure of the market: Berlin is a point to point city with a large low cost base, not a connecting airport. easyJet was expected to become the largest carrier by routes before the pandemic. Ryanair said it would not move into the new building in 2019 and stayed in the old Schönefeld terminal, then moved to Terminal 2 in 2022 when Terminal 5 closed.
| Rank in list | Destination | Passengers | List |
|---|---|---|---|
| 1 | Frankfurt | 1,180,261 | Domestic |
| 2 | Munich | 900,468 | Domestic |
| 3 | Stuttgart | 349,595 | Domestic |
| 4 | Düsseldorf | 264,393 | Domestic |
| 5 | Cologne Bonn | 252,813 | Domestic |
| 1 | Amsterdam | 811,041 | Europe |
| 2 | Palma de Mallorca | 779,767 | Europe |
| 3 | Zurich | 756,743 | Europe |
| 4 | Paris Charles de Gaulle | 715,768 | Europe |
| 5 | Istanbul | 597,287 | Europe |
Frankfurt and Munich are connections, not tourism, and they show how much long haul traffic leaves the country on a short flight first. Amsterdam, Zurich and Paris are the same pattern. Palma de Mallorca is the one pure leisure route on the list.
| Rank | Destination | Passengers | Detail |
|---|---|---|---|
| 1 | Antalya | 737,881 | Turkey |
| 2 | Istanbul Sabiha Gökçen | 416,657 | Turkey |
| 3 | Doha | 344,482 | Qatar Airways, up 78.8 percent |
| 4 | Tel Aviv | 308,561 | Israel |
| 5 | Hurghada | 221,613 | Egypt |
| 6 | Izmir | 218,859 | Turkey |
| 7 | New York JFK | 141,459 | Delta, summer schedule, new in 2023 |
| 8 | New York Newark | 132,253 | United |
| 9 | Singapore Changi | 85,958 | Scoot |
| 10 | Cairo | 77,524 | New in 2023 |
The intercontinental table is short because the market is short. Antalya, Sabiha Gökçen, Hurghada and Izmir are holiday routes. Doha is the Gulf connection. New York is the only American pair, served by Delta to JFK in the summer schedule and by United to Newark. Singapore is the only Asian entry in the top ten, at 85,958 passengers, and the article notes that Scoot's service to Singapore resumed after the pandemic. Hainan Airlines flies to Beijing Capital, but the route does not appear in the 2023 top ten.
In 2021 the airport authority said it wanted 25 long haul routes by 2025, including a revised bilateral agreement that would let Emirates serve a fifth German city. The growth that did arrive was American: United returned with Newark and added Washington Dulles in 2023, and Delta returned to JFK for the summer schedule.
A Six Track Station Under the Concourse
More than half of the airport's passengers arrive or leave by public transport, and the reason is a station directly under Terminal 1 with six tracks and a train every 20 minutes on two S-Bahn lines.
The terminal sits above a 3.1 kilometre east west railway tunnel that runs under the apron and the building. The nine tunnel sections were the first structures built on the site, excavated conventionally before the terminal existed. The station has six tracks. Two are used by the S-Bahn, with lines S9 and S85 each serving the airport every 20 minutes. The other four are used by Regional Express, the Airport Express known as FEX, and long distance trains including InterCity.
The FEX runs to Südkreuz, Potsdamer Platz and Berlin Hauptbahnhof. The article gives the journey to the main station as 22 minutes in one caption and about 23 minutes in the text. Before December 2025 the trip took 30 minutes. The opening of the upgraded Berlin to Dresden railway in December 2025 shortened it. InterCity trains run several times a day to Chemnitz, Dresden and Rostock via central Berlin.
The stations were renamed in December 2023. Terminal 1 and 2 became BER Airport station, and Terminal 5 became Schönefeld (bei Berlin) station. The new airport grew around the old one, and the railway names had to be untangled afterwards.
The gap in the U-Bahn
Line U7 terminates at Rudow, short of the airport, and there are plans to extend it if the money appears. The complication is that the line would cross the state border between Berlin and Brandenburg, and it is not clear who would pay for construction, operation and maintenance on which side. There is no provision for a U-Bahn station underneath the terminal.
The bus network fills the gap. Express buses X7, X71 and X11 serve the airport. X7 connects to the U7 at Rudow, X71 runs to Alt Mariendorf along the U6 via Rudow, and X11 continues to Lichterfelde West and Dahlem. Two special express buses, BER1 and BER2, charge a surcharge and run to Rathaus Steglitz and Potsdam main station.
By road the airport is reached from the A113 and the B96a. The A113 has a dedicated exit for Terminals 1 and 2 and connects to central Berlin through the A100 and to the A10 ring, from which the A13 continues south towards Dresden. There are more than 10,000 parking spaces in multi storey and ground level car parks, plus a short stay area of about 300 spaces in front of Terminal 1 for pick up and drop off. Rental cars are collected and returned at the P2 car park and car sharing sits at P4.
Bicycle access is the weakest link. The local cycling association, the ADFC, considers it lacking and has asked for a bicycle highway. The plans drawn up in 2006 made no provision for one.
Five Hours Without Movements, and the Villages Under the Flight Path
Takeoffs and landings are prohibited between 00:00 and 05:00. That is a narrower ban than the neighbours wanted, and the argument about it began before the airport opened.
The operating licence contains a night flight ban from midnight to 05:00. Residents went to the Federal Administrative Court to have it extended from 23:00 to 06:00, and on 13 October 2011 the court rejected the claim. It did rule that affected residents should receive additional noise insulation.
The route dispute is angrier. In September 2010 Deutsche Flugsicherung published arrival and departure routes that differed significantly from the ones used in the court decision that granted the construction permit. The original maps showed aircraft taking off and landing parallel to the runway. The new plans had flight paths deviating by 15 degrees, which put them over Lichtenrade, Steglitz and Zehlendorf in southern Berlin, and over Teltow, Stahnsdorf, Kleinmachnow and Potsdam in Brandenburg. Residents had not been told, and the response was a wave of protests and a lawsuit that the courts rejected.
The noise issue is also a land use issue. The construction permit was granted on the condition that fewer people would live under the approach path than lived around Tegel, Schönefeld and Tempelhof. That condition is the legal reason the old airports had to close, and it is why the single airport concept was not simply a preference for a bigger building. Berlin could not keep Tegel open and claim the noise benefit at the same time.
Cargo, Hangars, a Government Terminal and an Exhibition Hall
The passenger terminals take up a small part of the 1,470 hectares. The rest is cargo, maintenance, government aviation, an exhibition centre and land zoned for business parks.
The cargo facility was built in modules. The first has a capacity of 60,000 tonnes a year, and with all planned expansions it could handle up to 600,000 tonnes. In 2025 the airport actually moved 52,293 tonnes. The freighter map is short: ASL Airlines France and FedEx Express fly to Paris Charles de Gaulle, Singapore Airlines Cargo serves Amsterdam, Brussels, Frankfurt and Munich, and UPS Airlines flies to Cologne Bonn and Gdańsk.
| Operator | Destinations |
|---|---|
| Singapore Airlines Cargo | Amsterdam, Brussels, Frankfurt, Munich |
| FedEx Express | Paris Charles de Gaulle |
| ASL Airlines France | Paris Charles de Gaulle |
| UPS Airlines | Cologne Bonn, Gdańsk |
The two large hangars were built for Lufthansa and Air Berlin, each with room for maintenance on four or five narrow body aircraft. The government terminal was inaugurated and put into use on 21 October 2020. It was built as an interim facility for about 70 million euros after the plan for a permanent building, estimated at another 344 million, was cancelled in December 2019 until at least 2030.
The control tower is 72 metres tall, which makes it the third highest in Germany after Munich and Düsseldorf. It opened on 25 March 2012, replacing the tower at Schönefeld, and it is run by Deutsche Flugsicherung, which is responsible for air traffic control and apron control. Technical control, meaning power supply and IT, went into operation on 16 March 2018.
The Berlin ExpoCenter Airport opened on the south eastern part of the site on 3 July 2012. Messe Berlin operates the 250,000 square metre facility, which exists mainly for the biennial ILA Berlin Air Show. Around the terminal, 16 hectares are zoned as BER Airport City, and to the north the BER Business Park Berlin is planned across 109 hectares.
The Infotower, a 32 metre observation tower with a museum and a gift shop, opened on the construction site on 14 November 2007. It was closed and demolished in 2016, four years before the airport opened.
From Manila to Berlin: What the Route Map Actually Says
No Philippine city appears in the route tables. A passenger from Manila reaches Berlin through a hub, and the article's own figures show which hubs carry the traffic.
The destination list is long, but it is mostly European. The intercontinental table is ten routes, and the only Asian entry is Singapore Changi at 85,958 passengers in 2023. Doha is third on the same table at 344,482, and Istanbul is the fifth largest European route at 597,287, with Sabiha Gökçen adding another 416,657 on the intercontinental side. Those three are the realistic connections for a traveller from Manila: Qatar Airways through Doha, Turkish Airlines through Istanbul, or Scoot through Singapore. None of those is a Philippine route; they are the hubs that make the journey possible.
The absence is not surprising when you look at the traffic. Berlin is the third busiest airport in Germany and the twenty fourth in Europe, but its long haul market is thin and seasonal. The United States is served by United to Newark and, seasonally, by Delta to JFK. The Gulf is served by Qatar Airways to Doha. Asia is served by Hainan Airlines to Beijing Capital and by Scoot to Singapore, and neither appears in the 2023 top ten. An airline deciding where to fly from Berlin is looking at an area of 6 million people with no hub carrier, competing against Frankfurt and Munich for the same connecting passengers.
Cargo follows the same geometry. The four operators in the article fly to Paris Charles de Gaulle, Amsterdam, Brussels, Frankfurt, Munich, Cologne Bonn and Gdańsk. There is no freighter route to Manila, Hong Kong, Taipei or Seoul in the table. A Philippine air shipment reaches Berlin through a hub, not on a direct freighter. The airport's total cargo of 52,293 tonnes in 2025 is small next to Frankfurt or Amsterdam, and the article's own expansion ceiling of 600,000 tonnes is a plan, not a current figure.
What that means for a Philippine supplier
Berlin is a destination market, not a freight gateway. A programme for a German buyer ships into a European hub and clears customs there, then moves inland. The transit time is set by the hub connection and the road leg, not by the flight to Berlin. Plan the hub, not the last 400 kilometres.
What a Berlin Buyer Needs From a Philippine Factory
RB Advertising manufactures in Tagum City and Cagayan de Oro, in the southern Philippines. Berlin is a market where the product has to be specified properly, because the buyer is comparing a documented programme with suppliers closer to home.
The buyers who wear uniforms in Berlin are not one industry. Hotels and restaurants, retail groups, security firms, facility management, logistics operators, hospitals and the airport itself all buy clothing on a schedule. Some need front of house uniforms, some need workwear, some need high visibility garments. The common thread is that the order repeats, and the second order has to match the first.
That is the part of the business we are built for. Corporate uniforms across office, front desk, retail, security and facilities roles, with reorder continuity so that a style can be repeated in the same shade two years later. Industrial and high visibility workwear to a specification, which is a different construction from the heat and humidity work we do for Philippine buyers. Technical and performance garments, including sublimation, compression and rashguard construction. Branded merchandise and corporate gifts produced to a date.
The honest constraints
There is no nonstop flight between Berlin and the Philippines, and there is no direct freighter lane. A sample reaches Berlin through a hub, usually in the Gulf or in western Europe, and the same is true of a production shipment. That adds transit time compared with a Turkish or Portuguese factory, and it is the thing to plan around rather than the unit price.
We do not hold German warehousing, we do not have a Berlin sales office, and we cannot match a local decorator on a 48 hour rush job. What we can do is make a programme properly, document it, and repeat it. For a hotel group opening a property on a fixed date, or a facilities company that reorders every quarter, that is the useful part.
The practical conversation is about three dates: when the sample has to be approved, when production has to finish, and when the goods have to clear customs in Europe. Work backwards from the third date and the first two become obvious. The rest is specification, sizing and a purchase order that says exactly what was agreed.
Where the fit is real: multi property hospitality groups, retail chains with a uniform standard, security and facility management firms that need a durable replenishment supply, and logistics operators that need workwear in consistent sizes. Programmes, not one off orders. That is the honest boundary.
Frequently Asked Questions About Berlin Brandenburg Airport
Fourteen questions about the opening, the terminals, the runways, the trains and the routes, answered from the same record used above.
01When did Berlin Brandenburg Airport open?
It opened for commercial traffic on 31 October 2020. The airport was originally planned to open in October 2011, five years after construction began in 2006, so the opening came nine years after the first published date. The operating licence was issued in May 2020.
02Why was Berlin Brandenburg Airport delayed?
The most significant cause was the fire protection and alarm system. It was not built to the construction permit, failed the mandatory acceptance test, and had to be rebuilt in three sections. The airport proposed up to 700 human fire spotters as an interim measure and the Dahme-Spreewald building authority rejected it. Poor workmanship, an insolvent general planner and a fire system designer who was not a qualified engineer all added to the delay.
03How many terminals does BER have?
Two are in passenger service: Terminal 1, which opened in October 2020, and Terminal 2, which opened on 24 March 2022. Terminal 5, the former Schönefeld terminal, closed on 22 February 2021 and was confirmed as permanently closed in November 2022. A Terminal 3 has been planned but not built.
04Which terminal do Ryanair and Wizz Air use at BER?
Terminal 2. Ryanair was the primary tenant when Terminal 2 opened on 24 March 2022, and Wizz Air moved its operations there in November 2022. Eurowings, which had been expected to use Terminal 2, stayed in Terminal 1.
05How many runways does Berlin Brandenburg have?
Two parallel runways, 1,900 metres apart. The northern one, 06L/24R, is 3,600 metres of asphalt concrete and is the old Schönefeld runway, in use since the 1960s and lengthened for the new airport. The southern one, 06R/24L, is 4,000 metres of concrete and was commissioned on 31 May 2012.
06Why were the BER runways renamed in 2024?
Because of a shift in the Earth's magnetic field. On 3 October 2024, 07L/25R became 06L/24R and 07R/25L became 06R/24L. Runway numbers are magnetic headings rounded to the nearest ten degrees, so they change when the compass does, not when the pavement does.
07What happened to Tegel and Schönefeld airports?
Tempelhof closed in 2008. Schönefeld's passenger buildings were refurbished and became Terminal 5 on 25 October 2020, then closed on 22 February 2021 and never reopened. The last airlines completed their move from Tegel by 8 November 2020. Berlin Brandenburg has been the only commercial airport serving Berlin and Brandenburg since then.
08Is there a night flight ban at BER?
Yes. The operating licence prohibits takeoffs and landings between 00:00 and 05:00. On 13 October 2011 the Federal Administrative Court rejected a residents' claim to extend the ban from 23:00 to 06:00, and ordered additional noise insulation instead.
09How do you get from BER to central Berlin?
By train from the station under Terminal 1. The Airport Express, FEX, runs to Südkreuz, Potsdamer Platz and Berlin Hauptbahnhof in 22 minutes according to one figure in the article and about 23 minutes according to the text. S-Bahn lines S9 and S85 each run every 20 minutes. Before December 2025 the trip took 30 minutes, until the upgraded Berlin to Dresden railway opened.
10How many passengers did BER handle in 2025?
26,050,880 according to the infobox, up 2.3 percent, or 26,050,740 according to the annual table, up 2 percent. The two figures appear in the same article and differ by 140 passengers. There were 193,042 aircraft movements and 52,293 tonnes of cargo.
11Does BER have flights to the Philippines?
No. No Philippine city appears in the route tables. Passengers connect through Doha with Qatar Airways, through Istanbul with Turkish Airlines, or through Singapore with Scoot. There is no nonstop service and no direct freighter lane in the cargo table.
12Which airlines have bases at BER?
Condor, easyJet, Eurowings and Sundair operate bases at the airport. Lufthansa does not use Berlin Brandenburg as a hub. Air Berlin planned to build a hub there but filed for insolvency on 15 August 2017 and collapsed on 27 August, before the airport opened.
13How much did Berlin Brandenburg Airport cost?
The 2009 construction budget was 2.83 billion euros. Spending reached 4.3 billion by late 2012 and 5.4 billion by 2015. A 2015 projection including an EU aid request came to 6.8 billion. A January 2018 request that included expansion to 2030 took the total to 9.4 billion, or 10.3 billion with overheads. The figures measure different scopes at different dates.
14Is BER the only commercial airport in Berlin?
Yes. It is the only commercial airport serving Berlin and the surrounding state of Brandenburg, an area with about 6 million inhabitants. It replaced Tempelhof, Schönefeld and Tegel, and much of Schönefeld's infrastructure, including a runway, was reused.
Talk to the RB Advertising Team
Four channels, one sales desk. Tell us what you are making, where it ships, and when you need it.
Fastest route for quotes, samples and production questions.
Chat on WhatsAppBusiness hours: Mon to Sat, 8:30 AM to 5:00 PM